Sample case 1 of 8 · Container terminal · West Africa
Eighteen percent more boxes through the same eleven cranes.
The problemBerth productivity had stalled at 22 moves an hour while volumes grew 9% a year. The board was being pitched a $140M crane order.
What we didWe rebuilt the yard plan around vessel windows, moved reefer stacks closer to the quay, and re-rostered crews to the arrival curve instead of fixed shifts.
Berth moves per hour+7
Before22
After29
+18%throughput
22→29moves per hour
$140Mcrane order cancelled